The Federal Government has announced the completion of the
first phase rehabilitation of the Third Mainland Bridge.
There will also be an 18-hour total closure of the bridge
this weekend.
The Federal Controller of Works in Lagos, Olukayode Popoola,
during an inspection of the bridge noted that the fixing of six expansion
joints on the Oworonshoki-bound carriageway had been completed.
Popoola said the closure was necessary, so that debris would
be cleared from the section and construction would move to the Island-bound
carriageway.
The 18-hour closure would begin from midnight on Saturday
through Sunday. By midnight of Sunday, the total closure would be removed and
the partial closure would return.
“The diversions will still be at the same previous points.
“Work is to commence
on the Island-bound lane of the bridge with the partial closure of Adekunle to
Adeniji Adele Phase B.
“The repair work is to commence between 22nd of November,
2020 and 22nd of February, 2021 for a duration of three months,” he said.
Click to signup for FREE news updates, latest information and hottest gists everyday
Advertise on NigerianEye.com to reach thousands of our daily users
No comments
Post a Comment
Kindly drop a comment below.
(Comments are moderated. Clean comments will be approved immediately)
Advert Enquires - Reach out to us at NigerianEye@gmail.com