Two years and two months after the groundbreaking ceremony
of the $1.5billion Lagos-Ibadan standard gauge rail project, the Federal
Government at the weekend declared the project 70 percent completed from
Ebutte-Metta, Lagos to Ibadan, Oyo state.
The minister of Transportation, Rotimi Amaechi, however, said
from Ebutte-Metta to the Lagos Port in Apapa, the project is about 10 – 15
percent completed.
The project was originally designed from Ebute-Metta to
Ibadan but the minister extended it to Apapa to make it possible for mass
movement of cargos in order to reduce the prevalent congestion in the port.
Amaechi spoke at the weekend during the inspection of the
project as well as a valedictory project steering committee meeting held with
the contractor, the Civil Engineering and Construction Company (CCECC) in Papalanto,
Ogun state.
Amaechi on Friday and Saturday led officials of the Ministry
and the Nigerian Railway Corporation (NRC) led by its Managing Director, Engr.
Fidet Okhiria on the inspection which took them to Apapa Port and Ibadan on
Friday and Saturday.
The minister said on Friday that track laying for the
project had reached 123 out of the 156-kilometre stretch of the project, adding
the track laying would soon get to Ibadan.
It was gathered that virtually all the civil works
comprising 21 bridges have been completed; all beams erected. Also, it was
observed on Saturday that a new bridge has been constructed at Costain ahead of
the demolition of the existing bridge which was earlier earmarked for
demolition.
According to the NRC
MD, a new bridge in Jibowu will soon be constructed to replace the existing one
marked for demolition. Similarly, the team inspected the construction of
stations which have also reached advanced stage except for Apapa station where
some properties were to be demolished to give way for expansion and future
developments.
The minister, however, directed the NRC to evaluate the
properties leased out by the corporation to many companies and businesses in
Apapa, saying those whose leases had expired would be sent packing while those
with existing leases would be duly compensated.
He said there is a need to create more room for the station in
Apapa to accommodate shopping complex and hotel in future.
An emotional Amaechi said despite the humongous challenges
experience in the Lagos corridor, he was satisfied with the progress of work.
“What is critical in life is that if you are given an
assignment, do everything possible to deliver it. We have had confrontations
here and there, we have had challenges.
The first challenge we had was from Lagos State and in the
process of finding a solution, the challenges we met in the Lagos sector of the
construction delayed the speed in Lagos”, he said.
The minister said he felt gratified that the project got to
Lagos from Abeokuta, Ogun state.
“I thank all of you who participated in the process and wish
you luck if I don’t return to the cabinet or if I return to the cabinet and I
don’t return to the Transport Ministry, that is for the President to decide”,
he said.
Xia Li Jun, Deputy
Project Manager of CCECC, lauded the minister for providing the right
leadership which also encouraged the company to work night and day to deliver
the much it has achieved.
Click to signup for FREE news updates, latest information and hottest gists everyday
Advertise on NigerianEye.com to reach thousands of our daily users
No comments
Post a Comment
Kindly drop a comment below.
(Comments are moderated. Clean comments will be approved immediately)
Advert Enquires - Reach out to us at NigerianEye@gmail.com